1.1.1 Process and mechanical data: The main technical documents to be provided at the time of bidding, including but not limited to the following:
Equipment assembly drawing and assembly drawing of each component
List of consumable parts, replacement cycle and life
Equipment technical specifications and performance indicators
Total weight of induction melting furnace and weight of each component
1.1.2 Electrical and control data
Control system hardware list
Control system software list;
Control system hardware system data;
List of all instruments in the automatic control system and instructions for use;
List of all actuators in the automatic control system and instructions for use;
Control system network diagram and communication function description;
Two-year spare parts list;
List of bidders' information list;
1.1.3 Utility Information
Utility needs
Special requirements for utilities
1.2 Technical information provided after the start of construction
1.2.1 Process Information:
The main technical documents to be provided after winning the bid are in six copies, including but not limited to the following:
A set of two base maps larger than A3
The engineering design drawings are also provided with 2 sets of CD-ROMs, provided by the bidders AUTOCADR11/2001, and the texts are provided in WORD2003 version.
Equipment consumables detailed drawings
Equipment assembly drawing and assembly drawing of each component
Operation guide
Maintenance and overhaul instructions and plans
Equipment assembly and installation instructions
Lubricant Technical Description and Plan
Hydraulic technical description
starting program
Operational guidance
1.2.2 IF power supply electrical and control data
Hardware configuration diagram of the PLC control system;
I/O interface diagram of the PLC control system;
Control power supply system diagram of PLC control system;
The cabinet device layout diagram and terminal wiring interconnection diagram provided by the bidder;
a list of equipment and components provided by the bidder;
The list of power and control cables shall be given the starting point, number, model size and number of cores.
The function chart of the PLC control system;
Information point table of PLC control system;
PLC control software;
Configuration software and communication software for the color touch display operator terminal;
Control system commissioning, operating manuals and technical regulations;
Manuals for the use, installation, maintenance, commissioning, etc. of electrical and control equipment;
User programming manual for the PLC system.
Two-year spare parts list;
List of bidders' information list;
1.2.3 Utility Information